Sunday, October 30, 2011

Warren Road Project Start 12/11

Two weeks ago I started a new stone project keeping me busy. Also with Halloween me and my wife have been busy creating a new work of art. We showed off at our Halloween costumes at our good friends party 10/29/11. As you may have seen our Youtube with the Kia Soul Hamsters. This year we had to top last years costumes. Boy that was some hard work. Happy we can get back to sitting around and blogging.


I have been inspired by some of the most amazing clay models by Dan Snow. Some stone masons do hand drawling or us programs such as Sketchup. Others may use a drawling on a photo and some do nothing. This was my first clay model. I wanted to help my client see the wall more in 3 dimensional.


This wall at one time as most likely over 100 ft at 7 ft high. Over time the landscape changed along with the home. The wall became smaller, the old wall piled up on the driveway and around the property.


Pulling out the old wall using a pallet to make moving stone around easy.


Job site excavated. The rebuilt wall will be tied into the old wall section as I rebuild. The wall will have a curve to the right as seen in the model at the end of the blog. I will be working to build 9 - stile steps.


Top view looking down from old section. Pink lines wall build. Notice a few large stones in the earth which I will be building around.


Wall frames up 1:8 batter (every 8 inchs the wall will come in 1 inch.) This batter was closest to the old wall. This photo also shows my foundation. Pink paint marks curve.


The top of the wall frames marks 7 feet. The blue chalk line shows the curve. Notice how wide the wall is. Over 4 feet. The old wall was only 2 feet. Some would say this is way to small. But it is believe the wall has been on the property for over 100 years. With all the pins, chinks, tracer stones, limited batter, no ties I'm sure I missed something. My point the wall is still standing. Something to be said about those facts. Time shows all. My wall will out last the old section.


The clay model was created to show client the proposed wall with steps.


Our barn kitty Frolic is testing the back of the wall by applying the hydraulic pressure. Hard work I pay him well for making sure all my work stands up to his inspection. More to come as I make progress on the job.

Friday, October 14, 2011

Journeyman Testing DSC KY

The day after - (Sunday 10/2/11) the competitions at the Shaker Village KY. I started my day off working on organizing all my stone. My wall section had to be taken apart for a walk throw.

Wall before I started.

 Foundation, the day before my test I was able to tear out my wall section. I was able to build my foundation and organize all my stones.  I place my packing stones in piles close to the wall but spaced a foot or more away from the wall. Not to get in my way. A clean space around the wall keeps you clear from tripping over stone.

Cap stones are pulled of the wall and placed furthers away from the wall see the chair. All the stones in front of the chair are my cap stones. I set up my lines to tie in to the wall to the left which was a new section from the competition. The wall to the right was a old section I had to tie into. The stones I've sorted out in sizes. Large, medium, packing and stones I deemed to be junk or hard to work with. The wall had more packing stones then I could imagine. The building stones on the other side of the wall was on a down hill. I was told that the stone laid out to this side would be the preferred. Because when you strip out your wall section by section you would lay it out layer by layer. Put every method is up to the builder. This lay out on each side worked best due to the hill I was working on.  

This is a picture of how the the winners of the the event lay out their stones. One big pile and yes they grab what they need and work with what they have at hand. You could say this is one very efficient system with no wasted energy.  It may take years before some of us will get to this level or should I say if we get to this. The key is to read the stones and build with what you have. 

A old timer showed up named Stanley. This guy has built more stone stuff then you could imagine. When I say that I truly mean this. WAIT AND SEE!!! He only lives 1 mile from Shaker Village. I will be sure to do a full blog and the Raw Video I have. Watch for more to come. The best time I spent was taking a break to learn and see some one else work. 


The next day Monday I started building me wall section for my timed DSC journeyman test.  I was off to a very slow start. Thinking way to much. I stopped only a few times to take a drink and take a photo. I was very pleased with my start. But what I realize was I was behind. By noon I was still thinking about my stones. At 2 pm I was at the tie level. I don't know what I was doing with all my time. But at this point I got a big boost. I put it into high gear kept my mind in the game with the key rules. But I had to stop thinking about every little stone. Cover my joints length in...ect ect place the stone in the wall. At no time I was at the top. Ready for my cope stones. Time was not on my side since I spent the the morning thinking about what I was doing. Instead of following my instincts. 


For my journeyman section I had to build this 10 ft wall section within the day. The Sunday was not great since I was so close to the ticket window for the Shaker village. My big hat must have made me look like part of the entertainment. Truly I didn't mind Sunday. But by Monday. My head phones did not help the walker bys from avoiding asking questions like are you rebuilding the full wall or whens the competition... I should have said Wee parlay voo francay... Sure I don't know how to spell any of those words but I would have asked something in French. ANY way nothing would have stopped the passer bys. I just had to say I'm testing right now- I have to have this wall done today. As you can see I'm behind. (Ok can we watch) I should have said yes put the cash in the hat. But instead I said yes. For the most part people were very cool. But please don't put me any were around the tourist. Of course I don't plan to test again for a long time. I'll finish out my other special features and keep building to get my speed and accuracy up. Learning with one stone at a time.


This is the other side of my wall. I'm still waiting to get my official paper work. I enjoyed my time. I meet some great people and look forward to getting some feedback soon on my wall build.  Until then back to work. Making walls that look better then this grey field lime stone. I can say I will not miss this stone. I forgot how much I don't like this stone. But maybe if I was a local I it would grow on me.  I do enjoy the quarried or river lime stone much better. 

Kia Hamster - Halloween is comin' Yo!

2010 Kia Hamster Halloween!


Who's that guy in the Red?!

Wednesday, October 12, 2011

Index page-What's that?

WOW what a great Idea!
I started a index page in order to help navigate content better. Makes sense-Right?! Books have them why not web sites?

Hey Google maybe this should be a standard feature in your Blogger App. Just remember I was the first to tell you about the concept. I'm always thinking.

I will have the index page up by weekend.

Tuesday, September 20, 2011

How To - Read Stone Faces

Reading stones has taken me some time to understand. I feel the process is like learning a new language and I'm still learning. I love it!

I'm going to start with what I call gauged stone. I use this term since the stone I'm showing "Butler stone" happens to have similar sizes thickness. Such as 1",  3 inch high....ect...ect


The stone shown has a undercut. The Face ( face-the part of the stone which faces the out side of the wall -IE what you see) of the stone can be placed on the wall 2 ways (for conversation)


the correct (above)
or the incorrect. (below)

(notice how the stone tapers back at the bottom)

Working with your batter creates a structurally and visually correct wall. (batter - is the angle of the wall in which it may lean. My wooden frames leaning from left to right) 


The face of this stone should flow in the same direction as the batter. Not against it (above). A stone may fit great into your space -BUT-The stone above should be shaped by knocking off the undercut. Making the face a bit more flat. As time would have it - best to work with the stones as much as possible not against them. 



Moral of this blog - if your stone looks like this Flip it over to work with your batter not against. 

What do your stone faces look like?
---------------
Notes: How to read stone faces is a never endless topic. I will continue to talk about my journey to understand them. These views are only my opinion. 

Saturday, September 10, 2011

Testing / Tool List- level 1




Preparation: Level 1 testing (DSC)

Lay out rock sorted into function

Keep all hearting/infill within 24” of wall

Lay out rock similar to the way it comes off the old wall – especially near bottom

Copping stones are the furthest away when sorted

Lay coping stones out in the order they came off the wall

Make sure you have good tie stones available and set aside

Look through “new stone” for potential ties and copes or good foundation stones

You can even set these aside before the competition starts!


Building:

Leave 18” of clear space between wall foundation and rocks

Tie your own strings to the batter frames provided

Foundation – up and out by 4” (
Any protruding foundation measurements refer to Specification Sheet supplied on the day  of the competition. Normally 2 inch either side but check spec. )

Build a foundation that looks like a PATIO – extra points!

Try to place tie-in stones (to your neighbor) before they do

Place tie-in stones so that you zipper past the  line that is between you and  your neighbor

If you get ahead of you neighbor - keep building up and it is their responsibility to mesh with your zipper

Cover stones below copes at Shaker Village KY - 
always refer to spec on the day. 

When copping – follow the “random” patern of 2-1-2-1-2-1-2-1 – might need 35-40 (15-30 min to do)


General Stuff:

Neil says – for speed and efficiency – work with your shoulders perpendicular to wall

Keep your coarse work level

Don’t work stone too much – points deducted

Bigger stuff lower in the wall

Mossy side out

Work to the line but don’t touch the line (up and out)

Keep building up each side of the wall at the same time

Keep tools on top of wall so when you switch side you close to tools

Keep your hands moving constantly

If you are stuck  - Pack!

Shadows are better than loose fillers





Timing:

Get to site early and register early - (
Wether or not if you arrive to register for the competition first on site or 5 minutes before the comp starts there is no way to determine what section you might get. It's called the luck of the draw on the day. I have seen the worst section on the field turn out to be the winner of the competition, it all up to the skill  of the individual.)

Tear out should be done in 30 Minutes

Tie stones should be in by lunch break



Tool List:

* Small Cooler and water container

* String

*
Line Pins

* 
Small Pickaxe garden tool..ect (great for digging out the little stuff on for foundation)

* Pickaxe (one year the fellow next to me had to work throw tree roots to build foundation-ya fun!)

* Rock hammer ( the basic mason / brick hammer will do the job and any other you use often)

* 2 or 6lb sledge – short handle (busting stones if needed)

Chisel (if you use them - time limited during testing suggest avoid chiseling)

* Tape Measure

*
Gloves – 2 pair

* Safety glasses

Steel toed boots?

Head lamp (if you like to work in the dark)

Knee pads (if used- I find they slow me down for testing)

* Level (s) if used

* Buckets – Tubs

Grinder

Quickie saw

Large fan

Generator

Dynamite

Plastic explosives

Fuses

Gas grill

Cheer leaders

Motivational CD’s (Dan Snow)

Sherpa guides to carry all my stuff



NOTES: * = Yes  are a should have. Ha ha factor starts at Grinder and below....

This list above has been supplied by: 

Dale Mitchell
Mitchell Landscapes, LLC
WWW.MitchellLandscapes.com



Some information has been (added) or modified to help others plan for a great test day! 
DSC offers a on site port-a potti, rebar plus cross bars for top, string lines... but as a up and coming professional - I would advise you bring the needed tools you use on the day to day. If you have any questions ask the organization you are testing with. 


If your doing a special feature on site, make sure you bring your one wood for frames, rebar... go equipped and ask questions. 


DSWA level 2 notes:
I tested in spring this year. What did I some how forget? 3' or 4' level. Hard to build a cheek end (wall head) with out one. Ok maybe you can. I'm not that good. All other tools listed above. 








Tuesday, September 6, 2011

Tool - Line Pins


In UK you will know exactly what these are. I hear you can even go to the local hardware store to buy them. In the USA some might think this is a fancy butter knife. But no this is what they call a LINE PIN.







Line pins are used mainly for rebuilding old walls. Great to put into the stones past the area of your build. I don't use these much for new building. When you have nothing to attach your sting to - just put a line pin in between some stones. Tie your string. If you work with historical walls or will be testing in KY or VT. You should at least buy 4 of these to have. Allowing for one string line per side of the wall if you are building a free standing wall. 


The picture with the string wrapped has more string then it should. This could cause knots. A professional waller explained it best  to "hold the line pin at its middle, pinched between your thumb and fingers in your left hand. Then with your right hand in a figure of eight motion wrap the string around the head and then the spike of the pin in a continuos motion." Of-course not like mine!

Footprint Line Pins USA #220027

Affinity Tool Works, LLC
1161 Rankin
Troy, Michigan 48083
(866) 588-0395 Toll-Free(248) 588-0395 Phone
(248) 588-0623 Fax
I believe they cost me about $12-$16 ball park. Great folks. Tell them I sent you.